Cy4CEAWork with us

Cy4CEA grow lab: setup workplan

Everything needed to take Room 7551 from today's racks to 36 running cassettes, in the order to do it. Each task lists who does it, the parts by order-list number, the tools, the steps and how to know it is done. Tick the steps as you go.

Revision D, 17 November 2026Full build $205,623, all allowancesNothing is quoted or ordered yet

Start today

  1. Do task 0.2, the twelve measurements. It costs nothing and four of them change what you buy.
  2. Send the questions in task 0.3. Facilities answers take the longest.
  3. Ask for the four quotes in task 1.1.
  4. Order wave 1, the first-pair kit, about $11,352. This is stage 1. Do not order waves 2 or 3 until their stage has passed.

Ticks are saved in this browser only. They do not follow you to another computer and nobody else sees them. Track orders in the spreadsheet.

0 of 0 steps 0 Before spending1 Order2 Room3 Facilities4 Water5 Racks6 Cassettes7 First pair8 Panel9 Commission10 First crop11 Other bays12 Other zones13 RoutineOpen gaps

Build small first, then full scale

The lab is built in three stages. Each stage must pass before the next order is placed.

StageWhat is builtWhat it provesOrdersCostPass to go on
1. One pairTwo cassettes at the top tier of bay A1. Phases 5 to 10.Pump lift, the no-contact feed, dosing and probes, light, air, and the lift at the top tier.Wave 1$11,352Every test in task 9.3 passes. The cardboard mock-up in task 5.2 fits.
2. One bayThe other four cassettes of bay A1. Task 11.1.Six tanks and six pumps in one bay, the panel size, 36 devices on one bay computer. This is the unit that is copied.Wave 2$10,057Bay A1 passes task 9.3 on all six loops and grows one crop.
3. Full scaleBays A2, A3, A4, B1, B2. Task 11.2.Room heat and humidity, bay by bay.Wave 3$86,638Stop adding bays if the room passes 26 °C or 75 percent humidity.

Go or no-go for full scale

  1. Bay A1 has passed every test in task 9.3 on all six loops.
  2. Bay A1 has grown one crop to harvest.
  3. Facilities has confirmed in writing that the room can remove the heat and moisture.

Stages 1 and 2 together cost about $21,409, or 10 percent of the full build. Waves W, R and Z do not wait for the pilot, but each has its own condition in phase 1.


Spend in this order

Each phase ends with a lab that works. If the money stops, stop at the end of a phase, not in the middle of one.

PhaseWhat you buyCostRunning totalIf the money stops here
1. One pairTwo cassettes at tier 3 of bay A1 with everything: loops, light lift, blinds, bay panel, lab computer. Rack rework, stairs and the light meter.$17,572$17,572Two cassettes grow a crop under full control. Filled and drained by hose. Every design risk has been tested.
2. Bay A1The other four loops and cassettes of bay A1.$9,633$27,205Six independent loops. Enough for one small replicated trial.
3. Water, drain and batterySupply header, reverse osmosis, drain line, new circuits, three batteries, backflow preventer.$20,238$47,443Bay A1 fills and drains itself and rides through a power cut. The room is ready for more bays.
4. Rack ABays A2, A3 and A4 with their cassettes.$49,761$97,20424 loops on one rack. Four replicates of six treatments.
5. Rack BBays B1 and B2 with their cassettes, and the spare pumps.$33,694$130,898All 36 loops. The grow system is complete.
6. Lift and instrumentsMast lift, pull winch, shared camera, reference meters.$20,159$151,057One person can pull a tier 3 cassette. Until now that takes two people on the rolling stairs.
7. The rest of the roomRobot lockers, cage, benches, cameras, server cabinet, vine bay.$18,110$169,167The pot rows, the vine bay and the robot areas are fitted out.
8. Blackout on the other 17 pairsBlinds, panels, vents and switches for every pair after the first.$16,456$185,623Any pair can run its own day length. Before this, only the first pair can.
9. ReservesSoftware and fabrication help, freight and tax, ventilation, design reserve.$20,000$205,623Drawn on through every phase. Not a step to build.

A $175,000 plan: phases 1 to 6 plus the full reserves, $171,057. It defers phase 7, the rest of the room ($18,110), and phase 8, blackout on the other 17 pairs ($16,456). The first pair keeps its blackout. The lab can use its present benches and storage until phase 7 is funded.

Phases 1 to 7 plus the reserves come to $189,167. Blackout on every pair takes the total to $205,623, which is over $200,000. The order waves below split the same parts by supplier timing: wave 1 is phase 1 without the rack rework, stairs and light meter, which come from wave R. Wave 2 is phase 2, wave 3 covers phases 4, 5 and 8, wave W is phase 3, wave R is phase 6 plus the cassettes, and wave Z is phase 7.


The lab and the order of work

Plan of the lab from above. The water zone is on the west wall at the left. Racks A and B run east to west beside it. The robot floor is in the middle. Mung, saffron, the sink and planting are at the top. Harvest, storage, robotics, desks and the entry room are on the right.
The lab from above, north at the top. Water zone at the west wall, racks A and B beside it, bays numbered from the west. Model picture, not a survey.
Week 1
Phase 0. Measure, ask, request quotes. Order wave 1.
Weeks 2 to 3
Phases 2, 5 and 6 while parts arrive: clear the room, level rack A, build two cassettes. Bench-build the panel.
Weeks 4 to 5
Phase 7 and 8. Assemble the first pair in bay A1, tier 3. Phase 9 tests on water.
Weeks 6 to 7
Phase 10. One crop in the first pair, watched for two weeks. End of stage 1.
In parallel
Phases 3 and 4. Facilities work, then the water zone.
Stage 2
Order wave 2. Finish bay A1 and grow one crop in it.
Stage 3
After the go or no-go rule is met, order wave 3. About one bay a week.
Any time
Phase 12, the other zones.

The weeks are my estimate. I have not checked any lead time. The pump, the light bars and the lift are the likely long ones.

Racks, bays and tags. Racks are A and B. Bays count from the west wall: A1 to A4, B1 and B2. Tiers count from the floor: T1, T2, T3. A cassette is named by bay, tier and side: A1-T3-S is bay A1, top tier, south side. Every part of its loop carries that name.


Phase 0. Before spending week 1, no cost

0.1 Read and set up

Builder

Done when: You can find any part on this page in the spreadsheet.

0.2 Take twelve measurements

Builder, with a helper
#MeasureWhy it matters
1Gap between posts along each rack, every baySets the bay width. Three tanks with covers need about 38 in clear
2Height of the bottom rails above the floor, and clear height under where tier 1 will sitTanks are 12 in tall and need about 18 in with fittings
3Frame profile size and the caster threadPicks the levelling foot. Count the posts
4Ceiling height over the racks, to the lowest light, cord or sprinklerTier 3 bars hang at about 9 ft
5Existing channel width, height, hole spacing, and total usable lengthYou need 144 pieces of 32 in
6Water pressure at the west tap, with a gaugeThe RO unit needs 40 to 60 psi
7Where the lined trough at the west wall drains toMay remove the drain line across the aisle
8The building panel schedule, photographed with the door openSpare breakers decide the electrical cost
9Wattage on the label of one existing LED tube, and a countSizes one circuit
10Weight of one post and one beamChecks the tip-over figure
11Where each rack stands now: distance of two corners from two wallsDecides whether a rack has to move
12Aisle width on both sides of each rackThe lift needs 50 in

Tools 25 ft tape, 4 ft level, pressure gauge with a hose thread, phone camera, luggage scale.

Done when: All twelve are written down and photographed.

0.3 Send the questions

Builder drafts, lab lead sends
  • Can you fit a backflow preventer at the west tap, and at what cost?
  • May dilute fertiliser solution and RO reject water go down the floor drains? About 25 gal a day, and up to 60 gal on a change day.
  • Can the room have eight 20 A 120 V circuits with ground-fault protection, a ninth roughed in, and one 240 V 30 A outlet?
  • How much heat and moisture can the room's air system remove? The lab will add about 7 kW and up to 200 pints of water a day.
  • Where are the supply diffusers and return grilles? Can supply air be aimed at the middle rack aisle?
  • May we drill the slab for rack anchors?
  • Is any outlet on a generator?
  • Does equipment in the lab need a safety listing mark?
  • May a closed server cabinet stand in the grow room?
  • How may lab devices join the network?

Done when: Every question has a named person and a date sent in the logbook.

0.4 Safety rules for the build

Everyone

Done when: Each person who will build has read this list.

Six skills you will use everywhere

Gluing PVC pipe

  • Cut square with the PVC cutter. Wipe off burrs.
  • Push the dry parts together first and mark how deep the pipe goes.
  • Brush primer on both parts, then cement on both parts.
  • Push together with a quarter turn and hold for 30 seconds.
  • Wipe the bead. Follow the can for cure time. Do not put water on a joint the same hour.
  • Glue with the window or door open. The fumes are strong.

Threaded plastic fittings

  • Wrap PTFE tape three times round the male thread, in the direction the fitting turns.
  • Tighten by hand, then one more turn with a wrench. Plastic threads crack if forced.
  • Never use brass or galvanised parts in a nutrient line.

Push-fit tube

  • Cut the tube square with a tube cutter, not scissors.
  • Push it in until it stops. Pull back to check it has gripped.
  • To release, press the collar in and pull the tube.

Drilling a tank cover

  • Mark every hole from the real part, not from a drawing.
  • Clamp the cover to scrap wood. Use a step drill at low speed.
  • Deburr each hole. Test-fit before the cover goes on a tank.

24 V wiring

  • Red is +24 V. Blue or black is 0 V. Keep to it everywhere.
  • Strip 8 mm, fit a ferrule, crimp, and tug it.
  • One wire per terminal. Label both ends with the device tag.
  • Check every circuit with a multimeter before you connect power.
  • Power off and battery switch open before you touch a terminal.

Labels

  • Every tank, pump, valve, probe, riser and cable carries its tag, such as P-A1-T3-S.
  • The tag on the part, the tag on the wire and the name in the software are the same.

Phase 1. Order six waves, $205,623 in all

Buy in waves so that a failed test changes the later orders, not parts already on the shelf. Price tags: checked means the seller's page was open on 16 November. snippet means a search result only. get a quote means the figure is an estimate.

WaveWhatWhenCost
1First-pair kit: two loops, one panel, two cassettesNow$11,352
WWater zone, rack power, batteries, drain, electrical workWhen Facilities has answered$20,238
RRack rework, the other 34 cassettes, lift, stairs, instrumentsFeet and rack parts now. Lift after a quote$39,227
2The rest of bay A1: four more loopsStage 2: after the first pair passes phase 9$10,057
3Bays A2, A3, A4, B1, B2Stage 3: after the go or no-go rule is met$86,638
ZOther zones, vine bay, services and reservesAny time$38,110
Total$205,623

1.1 Ask for four quotes

Builder

Done when: Each quote is filed in Box and its price is in the spreadsheet.

1.2 Order wave 1, the first-pair kit

Builder, through the lab's purchasing route
IDItemMaker and partWhere to buyQtyEachCostPrice
A01Reservoir tank, 15 galTamco 6308U.S. Plastic2$105$210get a quote
A02Tank coverTamco 6358U.S. Plastic2$35$70get a quote
A03Circulation pump, 24 V DCXylem / Laing D5 Strong, Noryl housing (D5-38/810N family)Quote needed2$130$260get a quote
A04Pump speed trimgenericDigi-Key / Amazon2$15$30get a quote
A05Bulkhead fitting, 3/4 inBanjo TF075U.S. Plastic / Dultmeier2$11$22snippet
A06Suction and discharge kitgenericMcMaster-Carr2$60$120get a quote
A07Riser and return pipeworkgenericMcMaster-Carr2$80$160get a quote
A08No-contact feed nozzle setgenericMcMaster-Carr2$18$36get a quote
A09Sensor port in the return collectorgenericMcMaster-Carr2$12$24get a quote
A09bDrip pan under tier 2 and tier 3 cassetteslocal fabricationLocal fabrication2$45$90get a quote
A10Flow sensor, 1/2 inDIGITEN FL-408FAmazon2$10.49$21snippet
A11Fill solenoid valve, 1/2 in, 24 V DCElectricSolenoidValves PSL-15 24 VDCelectricsolenoidvalves.com2$55.96$112checked
A12Float valve, 1/2 inKerick MA052U.S. Plastic2$14.84$30checked
A13Drain valve, 3/4 in, motorisedU.S. Solid 3/4 in 2-wire auto returnussolid.com2$30.31$61snippet
A14Level switchMadison M8000PartsSource4$25.21$101checked
A15pH kitAtlas Scientific KIT-101PAtlas Scientific2$161.99$324checked
A16Conductivity kit, K 1.0Atlas Scientific EC-KIT-1.0Atlas Scientific2$240.50$481checked
A17Solution temperature probegeneric DS18B20Adafruit / Digi-Key2$10$20get a quote
A18Dosing pumpAtlas Scientific EZO-PMPAtlas Scientific8$87.99$704checked
A19Dosing tube and fittingsgenericMcMaster-Carr2$20$40get a quote
B01LED grow bar, 4 ft, whiteGE Current Arize Lynk2 GEHL48HBRI3Distributor quote6$70$420get a quote
B02Leader cable with dimming, 10 ftGE Current GECA30A18-CC10BDistributor quote1$35$35get a quote
B03Jumper cable with dimming, 2 ftGE Current GECA30A18-CF02BDistributor quote5$10$50get a quote
B04Plug-in relay for the lightsDigital Loggers IoT RelayDigi-Key / Amazon1$35$35get a quote
B05Light framegenericMcMaster-Carr1$40$40get a quote
B12Light lift motorSomfy Sonesse 30 DCT, ref 1241146Somfy dealer1$275.99$276snippet
B12bLight lift shaft kitRollease Acmeda CS4US spool and ribbonAV Outlet1$60$60get a quote
B13Frame height sensor and top switchgeneric VL53L1X classAdafruit / Digi-Key1$23$23get a quote
B14Blind motorSomfy Sonesse 30 DCT, ref 1241146Somfy dealer2$275.99$552snippet
B14bBlackout blind kitPhifer SheerWeave 7500 blackout clothAV Outlet or a local shade shop2$110$220get a quote
B15Fixed blackout panels and sealsgenericMcMaster-Carr1$90$90get a quote
B16Light-trap ventgeneric darkroom louvre classPhoto or HVAC supplier2$45$90get a quote
B17Blind closed switchgenericDigi-Key2$8$16get a quote
B06Bay fan, 120 mm, 24 VNoctua NF-F12 industrialPPC-24V-3000 SP IP67 PWMAmazon2$34.95$70snippet
B07Fan guards and frame bracketgenericDigi-Key2$15$30get a quote
B07bMoving cable loopgenericDigi-Key1$25$25get a quote
B08Fan speed controllerAdafruit EMC2101 breakoutAdafruit1$6$6get a quote
B09Air sensor, temperature and humidityAdafruit SHT41 (5776)Adafruit2$5.95$12checked
B10Light sensorAdafruit VEML7700 (4162)Adafruit1$4.95$5checked
B11Cassette seated switchgenericDigi-Key2$8$16get a quote
C01PLC CPUAutomationDirect C2-01CPUAutomationDirect1$110$110checked
C02Option module, 8 fast inputs and 6 outputsAutomationDirect C2-14D2AutomationDirect1$66$66checked
C03Input module, 16 x 24 V DCAutomationDirect C0-16ND3AutomationDirect2$69$138checked
C04Relay output module, 8 pointAutomationDirect C0-08TRAutomationDirect3$63$189checked
C05Analogue output module, 4 x 0-10 VAutomationDirect C0-04DA-2AutomationDirect1$175$175checked
C06Interposing relay and socket, 24 V coil, 10 AAutomationDirect 781 seriesAutomationDirect4$15$60get a quote
C07Bay computerRaspberry Pi Pi 4 Model B 4GBPiShop1$100$100checked
C08PoE+ HATRaspberry Pi SC1022PiShop1$29.95$30checked
C09SD card, industrial, and DIN mountgenericDigi-Key1$30$30get a quote
C10I2C multiplexerAdafruit TCA9548A (2717)Adafruit / Digi-Key1$6.95$7checked
C11Enclosure, 16 x 14 x 7 inIntegra H161407HCFLLSolutions Direct1$220.33$220checked
C12Back panel, DIN rail, terminals, fuses, wiregeneric ABP-1614 panelAutomationDirect1$150$150get a quote
C13Field connectors, M12 five-pinMurrelektronik 7000-12761-0000000 / 7000-12961-0000000AutomationDirect16$13.50$216checked
C14Dosing boxgenericPolycase / Integra1$120$120get a quote
C15Bay stock jugs and traygenericU.S. Plastic1$60$60get a quote
C16Leak sensor, 24 VGRI 2624Digi-Key / alarm supplier1$21.42$21snippet
C17Drip tray under the six tanksgenericU.S. Plastic1$60$60get a quote
C18CO2 sensorAdafruit SCD-41 (5190)Adafruit1$49.95$50checked
C19Hand-off-auto switch, one per pumpgenericAutomationDirect2$14$28get a quote
C20Motor input and output unitgeneric part not chosenAutomationDirect1$350$350get a quote
D0124 V supply with battery backup, 20 AMean Well DRS-480-24Digi-Key / Mouser1$230$230get a quote
D19Network cable and outdoor-rated patch leadsgenericany1$300$300get a quote
D22Lab control computergeneric part not chosenany1$700$700get a quote
E01Cassettelocal fabricationLocal fabrication2$310$620get a quote
E01bRotary latch, small, stainlessSouthco R4-10-10-101-20Southco shop2$28.88$58snippet
E01dStriker for the rotary latchSouthco R4-90-101-20Southco shop2$8$16get a quote
E01eGrip bar kitgenericMcMaster-Carr2$17$34get a quote
E01cHard stop and dock bar at each slotgenericMcMaster-Carr2$14$28get a quote
F09Calibration solutions, storage solution, spare probesAtlas Scientific ASPH4P-25, ASPH7P-25, ASPH10P-25, ASEC-K1.0, ENV-40-pHAtlas Scientific1$1,600$1,600get a quote
I04Hand tools and consumablesany1$600$600get a quote
Wave total$11,352

Done when: Every wave 1 line has an order date.

1.3 Receive and bench-test

Builder

Tools 24 V bench supply, multimeter, bucket, paint pen, label printer.

Done when: Every part has a tag and has passed its bench test.

Wave 2: the rest of bay A1, $10,057. Open for the line items.
IDItemMaker and partWhere to buyQtyEachCostPrice
A01Reservoir tank, 15 galTamco 6308U.S. Plastic4$105$420get a quote
A02Tank coverTamco 6358U.S. Plastic4$35$140get a quote
A03Circulation pump, 24 V DCXylem / Laing D5 Strong, Noryl housing (D5-38/810N family)Quote needed4$130$520get a quote
A04Pump speed trimgenericDigi-Key / Amazon4$15$60get a quote
A05Bulkhead fitting, 3/4 inBanjo TF075U.S. Plastic / Dultmeier4$11$44snippet
A06Suction and discharge kitgenericMcMaster-Carr4$60$240get a quote
A07Riser and return pipeworkgenericMcMaster-Carr4$80$320get a quote
A08No-contact feed nozzle setgenericMcMaster-Carr4$18$72get a quote
A09Sensor port in the return collectorgenericMcMaster-Carr4$12$48get a quote
A09bDrip pan under tier 2 and tier 3 cassetteslocal fabricationLocal fabrication2$45$90get a quote
A10Flow sensor, 1/2 inDIGITEN FL-408FAmazon4$10.49$42snippet
A11Fill solenoid valve, 1/2 in, 24 V DCElectricSolenoidValves PSL-15 24 VDCelectricsolenoidvalves.com4$55.96$224checked
A12Float valve, 1/2 inKerick MA052U.S. Plastic4$14.84$59checked
A13Drain valve, 3/4 in, motorisedU.S. Solid 3/4 in 2-wire auto returnussolid.com4$30.31$121snippet
A14Level switchMadison M8000PartsSource8$25.21$202checked
A15pH kitAtlas Scientific KIT-101PAtlas Scientific4$161.99$648checked
A16Conductivity kit, K 1.0Atlas Scientific EC-KIT-1.0Atlas Scientific4$240.50$962checked
A17Solution temperature probegeneric DS18B20Adafruit / Digi-Key4$10$40get a quote
A18Dosing pumpAtlas Scientific EZO-PMPAtlas Scientific16$87.99$1,408checked
A19Dosing tube and fittingsgenericMcMaster-Carr4$20$80get a quote
B01LED grow bar, 4 ft, whiteGE Current Arize Lynk2 GEHL48HBRI3Distributor quote12$70$840get a quote
B02Leader cable with dimming, 10 ftGE Current GECA30A18-CC10BDistributor quote2$35$70get a quote
B03Jumper cable with dimming, 2 ftGE Current GECA30A18-CF02BDistributor quote10$10$100get a quote
B04Plug-in relay for the lightsDigital Loggers IoT RelayDigi-Key / Amazon2$35$70get a quote
B05Light framegenericMcMaster-Carr2$40$80get a quote
B12Light lift motorSomfy Sonesse 30 DCT, ref 1241146Somfy dealer2$275.99$552snippet
B12bLight lift shaft kitRollease Acmeda CS4US spool and ribbonAV Outlet2$60$120get a quote
B13Frame height sensor and top switchgeneric VL53L1X classAdafruit / Digi-Key2$23$46get a quote
B14Blind motorSomfy Sonesse 30 DCT, ref 1241146Somfy dealer4$275.99$1,104snippet
B14bBlackout blind kitPhifer SheerWeave 7500 blackout clothAV Outlet or a local shade shop4$110$440get a quote
B15Fixed blackout panels and sealsgenericMcMaster-Carr2$90$180get a quote
B16Light-trap ventgeneric darkroom louvre classPhoto or HVAC supplier4$45$180get a quote
B17Blind closed switchgenericDigi-Key4$8$32get a quote
B06Bay fan, 120 mm, 24 VNoctua NF-F12 industrialPPC-24V-3000 SP IP67 PWMAmazon4$34.95$140snippet
B07Fan guards and frame bracketgenericDigi-Key4$15$60get a quote
B07bMoving cable loopgenericDigi-Key2$25$50get a quote
B08Fan speed controllerAdafruit EMC2101 breakoutAdafruit2$6$12get a quote
B09Air sensor, temperature and humidityAdafruit SHT41 (5776)Adafruit4$5.95$24checked
B10Light sensorAdafruit VEML7700 (4162)Adafruit2$4.95$10checked
B11Cassette seated switchgenericDigi-Key4$8$32get a quote
C06Interposing relay and socket, 24 V coil, 10 AAutomationDirect 781 seriesAutomationDirect8$15$120get a quote
C19Hand-off-auto switch, one per pumpgenericAutomationDirect4$14$56get a quote
Wave total$10,057
Wave 3: the other five bays, $86,638. Open for the line items.
IDItemMaker and partWhere to buyQtyEachCostPrice
A01Reservoir tank, 15 galTamco 6308U.S. Plastic30$105$3,150get a quote
A02Tank coverTamco 6358U.S. Plastic30$35$1,050get a quote
A03Circulation pump, 24 V DCXylem / Laing D5 Strong, Noryl housing (D5-38/810N family)Quote needed34$130$4,420get a quote
A04Pump speed trimgenericDigi-Key / Amazon30$15$450get a quote
A05Bulkhead fitting, 3/4 inBanjo TF075U.S. Plastic / Dultmeier30$11$330snippet
A06Suction and discharge kitgenericMcMaster-Carr30$60$1,800get a quote
A07Riser and return pipeworkgenericMcMaster-Carr30$80$2,400get a quote
A08No-contact feed nozzle setgenericMcMaster-Carr30$18$540get a quote
A09Sensor port in the return collectorgenericMcMaster-Carr30$12$360get a quote
A09bDrip pan under tier 2 and tier 3 cassetteslocal fabricationLocal fabrication20$45$900get a quote
A10Flow sensor, 1/2 inDIGITEN FL-408FAmazon30$10.49$315snippet
A11Fill solenoid valve, 1/2 in, 24 V DCElectricSolenoidValves PSL-15 24 VDCelectricsolenoidvalves.com30$55.96$1,679checked
A12Float valve, 1/2 inKerick MA052U.S. Plastic30$14.84$445checked
A13Drain valve, 3/4 in, motorisedU.S. Solid 3/4 in 2-wire auto returnussolid.com30$30.31$909snippet
A14Level switchMadison M8000PartsSource60$25.21$1,513checked
A15pH kitAtlas Scientific KIT-101PAtlas Scientific30$161.99$4,860checked
A16Conductivity kit, K 1.0Atlas Scientific EC-KIT-1.0Atlas Scientific30$240.50$7,215checked
A17Solution temperature probegeneric DS18B20Adafruit / Digi-Key30$10$300get a quote
A18Dosing pumpAtlas Scientific EZO-PMPAtlas Scientific120$87.99$10,559checked
A19Dosing tube and fittingsgenericMcMaster-Carr30$20$600get a quote
B01LED grow bar, 4 ft, whiteGE Current Arize Lynk2 GEHL48HBRI3Distributor quote90$70$6,300get a quote
B02Leader cable with dimming, 10 ftGE Current GECA30A18-CC10BDistributor quote15$35$525get a quote
B03Jumper cable with dimming, 2 ftGE Current GECA30A18-CF02BDistributor quote75$10$750get a quote
B04Plug-in relay for the lightsDigital Loggers IoT RelayDigi-Key / Amazon15$35$525get a quote
B05Light framegenericMcMaster-Carr15$40$600get a quote
B12Light lift motorSomfy Sonesse 30 DCT, ref 1241146Somfy dealer15$275.99$4,140snippet
B12bLight lift shaft kitRollease Acmeda CS4US spool and ribbonAV Outlet15$60$900get a quote
B13Frame height sensor and top switchgeneric VL53L1X classAdafruit / Digi-Key15$23$345get a quote
B14Blind motorSomfy Sonesse 30 DCT, ref 1241146Somfy dealer30$275.99$8,280snippet
B14bBlackout blind kitPhifer SheerWeave 7500 blackout clothAV Outlet or a local shade shop30$110$3,300get a quote
B15Fixed blackout panels and sealsgenericMcMaster-Carr15$90$1,350get a quote
B16Light-trap ventgeneric darkroom louvre classPhoto or HVAC supplier30$45$1,350get a quote
B17Blind closed switchgenericDigi-Key30$8$240get a quote
B06Bay fan, 120 mm, 24 VNoctua NF-F12 industrialPPC-24V-3000 SP IP67 PWMAmazon30$34.95$1,048snippet
B07Fan guards and frame bracketgenericDigi-Key30$15$450get a quote
B07bMoving cable loopgenericDigi-Key15$25$375get a quote
B08Fan speed controllerAdafruit EMC2101 breakoutAdafruit15$6$90get a quote
B09Air sensor, temperature and humidityAdafruit SHT41 (5776)Adafruit30$5.95$178checked
B10Light sensorAdafruit VEML7700 (4162)Adafruit15$4.95$74checked
B11Cassette seated switchgenericDigi-Key30$8$240get a quote
C01PLC CPUAutomationDirect C2-01CPUAutomationDirect5$110$550checked
C02Option module, 8 fast inputs and 6 outputsAutomationDirect C2-14D2AutomationDirect5$66$330checked
C03Input module, 16 x 24 V DCAutomationDirect C0-16ND3AutomationDirect10$69$690checked
C04Relay output module, 8 pointAutomationDirect C0-08TRAutomationDirect15$63$945checked
C05Analogue output module, 4 x 0-10 VAutomationDirect C0-04DA-2AutomationDirect5$175$875checked
C06Interposing relay and socket, 24 V coil, 10 AAutomationDirect 781 seriesAutomationDirect60$15$900get a quote
C07Bay computerRaspberry Pi Pi 4 Model B 4GBPiShop5$100$500checked
C08PoE+ HATRaspberry Pi SC1022PiShop5$29.95$150checked
C09SD card, industrial, and DIN mountgenericDigi-Key5$30$150get a quote
C10I2C multiplexerAdafruit TCA9548A (2717)Adafruit / Digi-Key5$6.95$35checked
C11Enclosure, 16 x 14 x 7 inIntegra H161407HCFLLSolutions Direct5$220.33$1,102checked
C12Back panel, DIN rail, terminals, fuses, wiregeneric ABP-1614 panelAutomationDirect5$150$750get a quote
C13Field connectors, M12 five-pinMurrelektronik 7000-12761-0000000 / 7000-12961-0000000AutomationDirect80$13.50$1,080checked
C14Dosing boxgenericPolycase / Integra5$120$600get a quote
C15Bay stock jugs and traygenericU.S. Plastic5$60$300get a quote
C16Leak sensor, 24 VGRI 2624Digi-Key / alarm supplier5$21.42$107snippet
C17Drip tray under the six tanksgenericU.S. Plastic5$60$300get a quote
C18CO2 sensorAdafruit SCD-41 (5190)Adafruit5$49.95$250checked
C19Hand-off-auto switch, one per pumpgenericAutomationDirect30$14$420get a quote
C20Motor input and output unitgeneric part not chosenAutomationDirect5$350$1,750get a quote
Wave total$86,638
Wave W: water zone, rack power and drain, $20,238. Open for the line items.
IDItemMaker and partWhere to buyQtyEachCostPrice
D0124 V supply with battery backup, 20 AMean Well DRS-480-24Digi-Key / Mouser2$230$460get a quote
D02Backup battery, 24 V 100 AhgenericQuote3$700$2,100get a quote
D03Battery cabinetgenericQuote2$350$700get a quote
D03bBattery disconnect and fusegenericQuote3$60$180get a quote
D04Demand pump, 115 VShurflo 2088-594-154Pump Agents1$180$180snippet
D05Pressure regulator and gaugegenericMcMaster-Carr2$45$90get a quote
D06Accumulator tank, 2 galgenericQuote1$60$60get a quote
D07Rack master fill valveElectricSolenoidValves PSL-15 24 VDCelectricsolenoidvalves.com2$55.96$112checked
D08Rack fill meterDIGITEN FL-408FAmazon2$10.49$21snippet
D09Supply header and dropsgenericMcMaster-Carr1$450$450get a quote
D10Reverse osmosis unitHydro-Logic Evolution RO1000Hydrobuilder / Hort supplier1$1,000$1,000snippet
D11Tote level sensingMadison M8000PartsSource3$25.21$76checked
D12Drain line and aisle coverCheckers Guard Dog GD1X75-B/B, two 36 in sectionsDiscount Ramps2$285.14$570snippet
D13Drain tube and fittingsJohn Guest PE-16 tubeSupplyHouse1$120$120snippet
D14Stock drums, 15 galU.S. Plastic 76680U.S. Plastic2$75.56$151checked
D15Spill tray for the drumsUltraTech 2328Grainger / Zoro1$189.99$190snippet
D16Backflow preventer and connectionFacilitiesISU Research Park / Facilities1$1,200$1,200get a quote
D17Emergency stop stationSchneider XALK178ERSP Supply1$108.06$108checked
D18PoE+ network switch, 24 portNetgear GS324TPv2Netgear1$249.99$250checked
D22Lab control computergeneric part not chosenany1$700$700get a quote
D21Water-zone panelAutomationDirect C2-01CPU + C2-14D2AutomationDirect1$520$520get a quote
D20Circuits and installationFacilitiesISU Facilities or an electrician1$11,000$11,000get a quote
Wave total$20,238
Wave R: racks, cassettes and handling, $39,227. Open for the line items.
IDItemMaker and partWhere to buyQtyEachCostPrice
E01Cassettelocal fabricationLocal fabrication34$310$10,540get a quote
E01bRotary latch, small, stainlessSouthco R4-10-10-101-20Southco shop34$28.88$982snippet
E01dStriker for the rotary latchSouthco R4-90-101-20Southco shop34$8$272get a quote
E01eGrip bar kitgenericMcMaster-Carr34$17$578get a quote
E01cHard stop and dock bar at each slotgenericMcMaster-Carr34$14$476get a quote
E02NFT channels and lids, reusedreuseCropKing1$1,800$1,800get a quote
E03Rack rework80/2080/20 / McMaster-Carr1$2,400$2,400get a quote
E04Levelling feet80/20 2200 (1/2-13), check thread on siteZoro / 80/2024$34.42$826snippet
F01Mast liftServerLIFT SL-500FXReseller quote1$14,000$14,000snippet
F02Pull winchgenericMcMaster-Carr1$300$300get a quote
F02bDeck docking kitlocal fabricationLocal fabrication1$200$200get a quote
F03Rolling stairs, 4 stepCotterman 1004R2630A3E10B3C2P6Zoro1$614$614snippet
F04Shared camera on a carriageEdmund Optics1$4,500$4,500get a quote
F05PAR meterApogee MQ-500Apogee1$580$580snippet
F07Handheld dissolved oxygen meterMilwaukee MW600TEquipment1$259$259snippet
F08CO2, temperature and humidity referenceVaisalaVaisala1$900$900get a quote
Wave total$39,227
Wave Z: other zones and reserves, $38,110. Open for the line items.
IDItemMaker and partWhere to buyQtyEachCostPrice
G01Robot lockerssee design page1$1,800$1,800get a quote
G02Roll-in cagesee design page1$1,500$1,500get a quote
G03TV and wall mountsee design page1$900$900get a quote
G04Desks and benchessee design page1$1,200$1,200get a quote
G05Pots on the robot floorsee design page1$600$600get a quote
G08Lab camera screen and three camerassee design page1$2,000$2,000get a quote
G09Door with a glass panelsee design page1$800$800get a quote
G10Floor tape and signssee design page1$300$300get a quote
G11Healing benchsee design page1$400$400get a quote
G12Charging and docking bayssee design page1$900$900get a quote
G13Server cabinetsee design page1$2,500$2,500get a quote
H01Strut channel, 1-5/8 in, 10 ftSuperstrut ZA1200HS-10Home Depot26$43.65$1,135snippet
H02Strut fittingsUnistrut P2072A, P1546, P1026Electrical supplier1$650$650snippet
H03High-wire hooks with twineJohnny's Rollerhook 7047Johnny's Selected Seeds1$35.30$35checked
H04Drip stakes, 2 L/hNetafim 01WPCJL2AW-24Hydrobuilder1$22.19$22snippet
H05Vine irrigation setgenericU.S. Plastic / McMaster-Carr1$450$450get a quote
H06Top light for vinesHLG Scorpion DiabloHLG2$1,299$2,598snippet
H07Side bar hangers and cordsgenericMcMaster-Carr1$320$320get a quote
I01Ventilation and moisture allowanceFacilities1$4,000$4,000get a quote
I02Fabrication, software and commissioning1$10,000$10,000get a quote
I03Freight and tax reserve1$3,000$3,000get a quote
I05Design reserve1$3,000$3,000get a quote
Wave total$38,110

Phase 2. Prepare the room weeks 2 to 3

2.1 Empty and strip the racks

Builder, with a helper

Tools Transfer pump, buckets, wrenches, zip bags for fasteners.

Done when: Both racks are bare frames. Channels are clean, counted and stacked.

2.2 Clear the floor and mark it

Builder, with a helper

The plan dimensions come from a model, not a survey. If the taped layout does not fit the room, stop and send the measurements before moving anything.

Done when: Racks sit on their taped outlines with 50 in aisles and the bay names on the floor.


Phase 3. Facilities work in parallel

3.1 Power

Facilities or a licensed electrician
Building panelFacilitiesL1Rack A lights, bays 1-26 pairs, 1.15 kW, 9.6 AL2Rack A lights, bays 3-46 pairs, 1.15 kW, 9.6 AL3Rack B lights, bays 1-26 pairs, 1.15 kW, 9.6 AC124 V supplies3 x 480 W, about 13 A at full loadW1Water zonedemand pump, RO, 3 AS1Server cabinetedge PC, switch, 4 AV1Vine top lights2 x 650 W, 11.7 AR1Robot docks and pot-row barsmeasure the bars24 V supplyDRS-480-24Battery24 V 100 AhBay panelfused 24 V branchesPumps, fans, valves24 V, at hand heightDosing pumpscut by "dose permit"two sets on rack A, one on rack B; batteries in a floor cabinetEmergency stopdrops L1-L3, fill, dosing. Pumps keep running
Eight circuits. Students build only the 24 V side, to the right of the supply.
Circuit, 120 V 20 AFeedsAmps
L1Lights, bays A1 and A29.6
L2Lights, bays A3 and A49.6
L3Lights, bays B1 and B29.6
C1Three 24 V suppliesabout 11
W1Demand pump, RO, water-zone panel3
S1Server cabinet4
V1Two vine top lights11.7
R1Robot docks, pot-row and vine side barsnot measured

Parts

  • D20 Circuits and installation · 1 lot
  • D17 Emergency stop station · 1

Done when: Every outlet is labelled with its circuit name and trips its ground-fault test button.

3.2 Water, drain and air

Facilities

Parts

  • D16 Backflow preventer and connection · 1
  • I01 Ventilation and moisture allowance · allowance

Done when: You hold written answers to all ten questions from task 0.3.


Phase 4. Water zone after the backflow preventer is in

A garden hose is enough for the first pair. Build this phase before bay A1 gets its other four loops.

4.1 Totes, filter and reverse osmosis

Builder

Parts

  • D10 Reverse osmosis unit · 1
  • D11 Tote level sensing · 3

Tools Tube cutter, PTFE tape, wrenches.

Done when: The tote fills, the RO unit stops by itself, and nothing drips.

4.2 Demand pump and header

Builder

Parts

  • D04 Demand pump, 115 V · 1
  • D06 Accumulator tank, 2 gal · 1
  • D09 Supply header and drops · 1 lot
  • D05 Pressure regulator and gauge · 2
  • D07 Rack master fill valve · 2
  • D08 Rack fill meter · 2

Tools PVC cutter, primer, cement, pipe hangers, drill, ladder or the rolling stairs.

Close the shut-off and open a drop to release pressure before you open any fitting on the header.

Done when: With the rack shut-offs open and every drop capped, the gauge holds 20 psi for 30 minutes and every joint is dry.

4.3 Water-zone panel, drums and spill tray

Builder

Parts

  • D21 Water-zone panel · 1
  • D14 Stock drums, 15 gal · 2
  • D15 Spill tray for the drums · 1

Done when: Wetting the floor sensor stops the pump and closes both master valves.


Phase 5. Racks weeks 2 to 3, rack A first

5.1 Levelling feet and tiers

Builder, with a helper
lift aislemiddle aislepostlevelling footslide supporttop beam
A cut through one bay, looking along the rack. Posts on levelling feet and three slide supports.

Parts

  • E04 Levelling feet · 24, count the posts
  • E03 Rack rework · 1 lot

Tools Jack or lever and blocks, wrenches, 4 ft level, luggage scale.

If a foot lifts or the rack rocks in the pull test, stop. Ask about anchoring before loading the rack.

Done when: The rack and every slide support are level, and no foot moves in the pull test.

5.2 Cardboard mock-up of one bay

Builder
T1-NT1-SPPT2-NT2-SPPT3-NT3-SPPjugs in a tray: A, B, pH-, pH+pump gap, 10 in:risers and downpipes abovenorth aislesouth aisleprobes face the aislebay panel and dosing boxon the post above, at 4 ftnorth tanks sit 10 in backbay about 41 in, to be measuredrack depth 5 ft 8 in
Under tier 1, from above. This is the fit the mock-up tests.

If the tanks do not fit, do not order wave 2. Send the measurements first.

Done when: You have photos of the mock-up and a yes or no on each of the three fits.


Phase 6. Cassettes two for the first pair, then 34 more

6.1 Build two cassettes

Fabricator or builder
35.0 frame36.5 overall32.0 channel30.6 frame8.08.08.03.33.64.08.08.08.09.814.41234678910HIGH END: water inLOW END: water outAISLE SIDE: the cassette slides out this waySPINE SIDE
Plan, from above. Dimensions in inches. Numbers in circles match the cut list.
#PartMaterialLengthQtyNote
1Runner1 in T-slot aluminium extrusion30.62Rides on the rack's slide strips. Square ends
2Front and back rail1 in T-slot aluminium extrusion33.02Fits between the runners
3Cross support1 in T-slot aluminium extrusion28.62Fits between the rails, near faces 9.8 and 24.2 from the high-end edge
4Channel with lidExisting NFT channel, reused32.04CONFIRM width and height. Drawn 4.6 wide, 1.6 tall
5Slope shimsFlat bar, 1 wide: one 3/4 thick, one 3/8 thick28.623/4 on the support nearer the high end, 3/8 on the other
6End cap and inlet collarCap to suit the channel; collar cut from 1 in PVC pipe3/4 tall4One set per channel, high end
7CollectorPVC channel or gutter, 1-1/2 wide × 2 deep32.51Outside the low-end runner. Open spout at the spine end
8Grip bar on a sliding stem1/2 round stainless bar on two stems through the front rail, with a return spring4.01Centred on the front rail. Slides 1/2 in before it pulls the frame. 1-1/2 clear behind the bar
9Rotary latchSmall stainless push-to-close rotary latch with a release lever1Under the front rail, at the grip bar. Its lever is joined to the bar by a link rod. See the buy table
10Magnet for the seated switchSealed magnet to match the reed switch1Back rail, spine side

Extrusion per cassette: 184.4 in, about 15.4 ft. For 36 cassettes: about 555 ft.

from the fixed nozzle0.8 fall53/4 shim53/8 shimSeen from the aisle. The frame is level. The two shims give the slope of 1 in 40 and lift the open ends over the runner.
Elevation from the aisle.
channellidend cap, sealedcollar: 1 in inside, 3/4 in tall, glued to the lid3/4 in hole through the lid2.0 to hole centre
Detail A. Inlet at the high end of each channel. The fixed nozzle on the rack ends 1/2 in above the lid, inside the collar.
channel, low end, opencollector: 1-1/2 in wide, 2 in deepfalls 3/4 in toward the spinechannel floor reaches 1/2 in over the collectorbracketed to the outside of the runnerAt the spine end the collector ends in an open spout 1.5 in past the frame.It pours into the fixed trough on the rack. Nothing connects.
Detail B. Collector at the low end.
Confirm on site before cuttingWhy
Channel width and heightDrawn 4.6 × 1.6 in from the model. Sets the cap, the clamps and whether four fit at 8 in spacing.
Clear gap along the rack at each slotThe cassette is 36.5 in overall. It needs at least 37.5 in clear between posts, cross beams and bay walls.
Slide strip spacing on the rackRunner centres are 34.0 in apart. Fit the rack's two slide strips to match.
Which end is high in each slotThe frame is the same either way. Fit the caps, shim and collector to suit the slot.
A rack beam under the front rail at each slotThe strike and the dock bar bolt to it. If there is none, add a 1 in extrusion between the two slide supports.
Existing lid and plant hole sizeThe lab's plugs decide the hole. Existing holes may not fall at 8 in spacing.

Parts

  • E01 Cassette · 2
  • E01b Rotary latch, small, stainless · 2
  • E01e Grip bar kit · 2
  • E02 NFT channels and lids, reused · from stock

Tools Mitre saw with a fine blade for aluminium, step drill, deburring tool, hex keys, square, tape, level.

Done when: Two cassettes slide in and out of the tier 3 supports by hand and latch.

6.2 Strike, hard stop and dock bar at each slot

Builder
rack beamslide support, beyondfront railcassette frame123456rotary latch: closes round the striker when pushedstriker, bolted to the rackgrip barstem, bushings and return springlink rod to the latch leverdock bar for the lift hookspullPulling the bar moves the link rod, which trips the latch lever and opens the jaw. The bar then pulls the frame. Pushed home, the jaw snaps shut by itself.
The bought parts in place. Numbers match the table.
#PartWhat to buyMaker and partWherePrice eachPrice basis
1Rotary latchSmall push-to-close rotary latch, single stage, stainless, with a release leverSouthco R4-10-10-101-20Southco shop$28.88seen in a search result
1Same latch, with a rubber bumperUse this version if the first rattlesSouthco R4-10-21-105-20Zoro$33.95seen in a search result
2StrikerSmall stainless striker for the R4 latch, on an angle bracketSouthco R4-90-101-20Southco shopabout $8my estimate
3Grip bar1/2 in round 304 stainless rod, cut 4 in long, ends roundedMcMaster-Carrabout $4my estimate
4Stems, bushings, springsTwo 1/4 in stainless shoulder screws about 2 in long, four nylon flanged sleeve bearings, two compression springsMcMaster-Carrabout $9my estimate
5Link rod1/8 in stainless rod with a clevis at each end, bar to latch leverMcMaster-Carrabout $4my estimate
6Dock bar1/2 in round stainless rod, 30 in, on two stand-off bracketsMcMaster-Carrabout $10my estimate
7Hard stopRubber bumper with a stud, at the spine end of the slotMcMaster-Carrabout $4my estimate
8Seated switchSealed reed switch and magnet. Order-list item B11Digi-Key$8allowance
9Frame extrusion1 in T-slot aluminium, 15.4 ft per cassette80/20 1010Steiner Electric, 97 in bar$35.89 a barseen in a search result
1Push inPush the cassette along the slide strips.The bolt hangs down under spring force.2Bolt rides overThe sloped face of the bolt meets the strike.The strike lifts the bolt. No hand action.3Latched and seatedseatedThe bolt drops behind the strike with a click.The frame meets the hard stop. The switch closesand the pump may start.spring bolt on the cassettestrike on the rackgrip barhard stop at the spine
Latching. Aisle on the left, spine on the right.
1At restseatedThe flat face of the bolt bears on the strike.The cassette cannot move toward the aisle.2Pull the grip bar 1/2 inThe bar slides 1/2 in on its stem and lifts the bolt.The cassette has not moved yet.3Keep pullingThe bar reaches its stop and now pulls the frame.The bolt passes over the strike.4Let goA spring returns the bar and drops the bolt.The cassette rolls on to the lift deck.spring bolt on the cassettestrike on the rackgrip barhard stop at the spine
Unlatching with one pull on the grip bar.
Latch testPass when
Push in and pull out 50 timesLatches every time with no hand on the bolt. Releases every time with one pull.
Pull on the frame with 50 lb, bar untouchedThe cassette does not move.
Release force at the grip barUnder 5 lb
Stop 1 in short of homeSeated switch stays open. The pump does not start.
Dock, load a full cassette, push the lift away by handThe deck stays on the bar.
Tilt test on the deckThe cassette stays on the deck with the catch up when the deck is lowered and stopped sharply.

Parts

  • E01d Striker for the rotary latch · 2 for the first pair, 36 in all
  • E01c Hard stop and dock bar at each slot · 2 for the first pair, 36 in all
  • B11 Cassette seated switch · 2

The latch is a first choice, not a tested one. If it behaves differently from the drawings, change the drawings before building the other 34 cassettes.

Done when: All six latch tests pass on both cassettes of the first pair.

6.3 Light lift and blackout on the first pair

Builder
drip pan of the tier above closes the topwinding shaft with a 24 V tube motor, four cordslight frame: six bars on two railslowest: 6 in above the channelshighest: 17 in, under the drip panfixed panelvent band witha light trapblackout blind,motor in the rollsouth aislevent band,light traptwo fans ride on the framesame blind onthis facemiddle aisle
One pair, cut across the rack. The light frame and its two fans ride up and down on four cords. Each aisle face closes with a blind. Bay sides and the top are fixed panels.
TestPass when
Run the frame from top to bottom 50 timesStays level within 1/4 in end to end; stops at both ends every time
Read the frame height at five positionsSensor within 1/2 in of a tape measure
Both blinds down, neighbours at full lightUnder 0.1 µmol/m²/s at the canopy; no light line at any edge
Air with both blinds downFlow at mid-canopy at least half of the open figure; humidity holds under the limit overnight
Pull a cassette with the blind downThe pull stays locked until the blind and frame are up

Parts

  • B05 Light frame · 1
  • B12 Light lift motor · 1
  • B12b Light lift shaft kit · 1
  • B13 Frame height sensor and top switch · 1
  • B14 Blind motor · 2
  • B14b Blackout blind kit · 2
  • B15 Fixed blackout panels and seals · 1
  • B16 Light-trap vent · 2
  • B17 Blind closed switch · 2
  • C20 Motor input and output unit · 1

The motor is a first choice, not a tested one. Buy three motors for this pair, prove them here, then order the rest. The motor is rated for dry rooms, so keep it under the drip pan. Keep fingers clear of the cords and the blind bar while a motor runs.

Done when: All five tests pass. The motor and blind part numbers that passed are written in the order list.


Phase 7. Build the first pair bay A1, tier 3, weeks 4 to 5

Tier 3 is the hardest case for the pump, the lift and the reach. Build it with water only. Each drawing is the same cut through the bay. New parts are amber. Do each step for the two tier 3 cassettes only, then run phase 9.

7.2 Tank deck and drip tray

Builder
lift aislemiddle aisletank deck with a 1 in lipleak sensor

Parts

  • C17 Drip tray under the six tanks
  • C16 Leak sensor, 24 V

Done when: Pour 1 L on the deck. It stays inside the lip and the sensor trips.

7.3 Tanks and covers

Builder
lift aislemiddle aisletank, south rowtank, north rowcover

Parts

  • A01 Reservoir tank, 15 gal
  • A02 Tank cover
  • A05 Bulkhead fitting, 3/4 in

Fill each tank with 2 in of water on the bench first and look for a weep at the bulkhead. It is far easier to fix there.

Done when: Six tanks fit between the posts with the covers on. A 10 in gap runs between the two rows.

pHECTlowhighreturn, 1½ infill and float valveABpH-pH+aisle endpump gap endCover 24 × 12 in, seen from above. Positions are a guide: mark from the real probe and valve bodies.The suction bulkhead goes in the tank wall at the pump gap end, not in the cover.
Drilling plan for a tank cover.

7.4 Pump trains and drain valves

Builder
lift aislemiddle aislepumppumpdrain valve

Parts

  • A03 Circulation pump, 24 V DC
  • A04 Pump speed trim
  • A06 Suction and discharge kit
  • A13 Drain valve, 3/4 in, motorised

A wet-rotor pump is destroyed by running dry. Do not power a pump until its tank holds water above the suction.

Done when: Fill the tank to 4 in. No drip at the bulkhead or the unions with the ball valve open.

Tank wallinner endBulkhead¾ in, 1½ in upBall valve¾ in PVCStrainer50 meshUnionPump24 V, floodedUnionTeeup: riser to the cassetteDrain valveclosed at restDrain line½ inWater runs left to right. Unions on both sides let the pump come out in minutes.No brass anywhere. Tighten unions by hand only.
The pump train, in order.

7.5 Risers and flow sensors

Builder
lift aislemiddle aisleriser, one per cassetteflow sensor

Parts

  • A07 Riser and return pipework
  • A10 Flow sensor, 1/2 in

Done when: Six risers per bay, each traced by hand from one pump to one cassette.

7.6 Nozzle rails

Builder
lift aislemiddle aislenozzle railfour nozzles

Parts

  • A08 No-contact feed nozzle set

If one nozzle runs weak, its tube is longer, kinked or partly blocked. Do not pinch the others to match.

Done when: Run the pump. Catch each nozzle in a cup for 30 seconds. The four agree within 15 percent.

channel, high endchannel capcollar round the inlet holerail, fixed to the rack frame¼ in tube, 24 in, all four equal½ in gapdrip catch, drains to this cassette's return
One nozzle over one channel inlet.

7.7 Return troughs, sensor ports and downpipes

Builder
lift aislemiddle aisletroughsensor portdownpipe to its own tank

Parts

  • A07 Riser and return pipework
  • A09 Sensor port in the return collector

Done when: Pour 2 L into each trough. All of it reaches the right tank.

7.8 Drip pans, tiers 2 and 3

Builder
lift aislemiddle aisledrip pan, slopes to the spinepan drain

Parts

  • A09b Drip pan under tier 2 and tier 3 cassettes

Done when: Pour 1 L into each pan. All of it reaches that cassette's tank.

7.9 Fill line

Builder
lift aislemiddle aislewater headerdropfill solenoid, then float valve

Parts

  • D09 Supply header and drops
  • A11 Fill solenoid valve, 1/2 in, 24 V DC
  • A12 Float valve, 1/2 in

Water pressure in the header is 20 psi. Close the rack shut-off before opening any fitting.

Done when: Hold a solenoid open by hand. The float valve stops the water below the high switch.

7.10 Drain line

Builder
lift aislemiddle aisledrain line, 1/2 in, to the floor drain

Parts

  • D13 Drain tube and fittings
  • D12 Drain line and aisle cover

Done when: Open one drain valve with the pump on. Water reaches the floor drain and nowhere else.

7.11 Probes and level switches

Builder
lift aislemiddle aislepH, EC, temperaturetwo level switches

Parts

  • A15 pH kit
  • A16 Conductivity kit, K 1.0
  • A17 Solution temperature probe
  • A14 Level switch

A pH probe that dries out is ruined. Leave the storage cap on until the tank has water.

Done when: Lift each float by hand. The right input changes on the controller.

7.13 Light bars, lift and relays

Builder
lift aislemiddle aislelight bars, six per pairrelay

Parts

  • B01 LED grow bar, 4 ft, white
  • B02 Leader cable with dimming, 10 ft
  • B03 Jumper cable with dimming, 2 ft
  • B04 Plug-in relay for the lights
  • B05 Light frame
  • B12 Light lift motor
  • B13 Frame height sensor and top switch
  • B10 Light sensor

The bars plug in. Do not cut a cord or open a bar. If a cord is too short, ask the electrician for a nearer outlet.

Done when: Nine light readings per cassette. The mean is 200 µmol/m²/s or more.

7.14 Fans

Builder
lift aislemiddle aisletwo fans per pair

Parts

  • B06 Bay fan, 120 mm, 24 V
  • B07 Fan guards and frame bracket
  • B07b Moving cable loop
  • B08 Fan speed controller
  • B09 Air sensor, temperature and humidity

The fan speed pin takes 5 V only. 24 V on that pin destroys the fan.

Done when: Under 2 °C rise from intake to exhaust with the lights at full.

7.15 Slide the cassettes in

Builder, with the lift or two people
lift aislemiddle aislecassette, four channelsseated switch

Parts

  • E01 Cassette
  • E02 NFT channels and lids, reused
  • B11 Cassette seated switch

Done when: Pull and reseat each cassette 20 times. The pump stops first each time. No drip reaches the tier below.

Part quantities: for the first pair, take the wave 1 quantity. Steps 7.1 and 7.12 are phases 5 and 8.


Phase 8. Bay panel on the bench, in parallel with phase 7

8.1 Lay out and mount

Builder

Parts

  • C11 Enclosure, 16 x 14 x 7 in · 1
  • C12 Back panel, DIN rail, terminals, fuses, wire · 1
  • C01 PLC CPU · 1
  • C02 Option module, 8 fast inputs and 6 outputs · 1
  • C03 Input module, 16 x 24 V DC · 2
  • C04 Relay output module, 8 point · 3
  • C05 Analogue output module, 4 x 0-10 V · 1
  • C06 Interposing relay and socket, 24 V coil, 10 A · 12, 4 for the first pair
  • C07 Bay computer · 1
  • C08 PoE+ HAT · 1
  • C09 SD card, industrial, and DIN mount · 1
  • C10 I2C multiplexer · 1
  • A04 Pump speed trim · 6, 2 for the first pair
  • C13 Field connectors, M12 five-pin · 16

Tools Drill, DIN rail cutter or hacksaw, screwdrivers, crimp tool, ferrules, wire in red and blue, label printer.

Do the panel on a bench, sitting down, over two or three days. Most faults come from rushing this step.

Done when: Everything is mounted, nothing overlaps, and the cover closes.

8.2 Wire it from the table

Builder
DeviceTagOn the wayLands on
PumpPFuse, then hand-off-auto switch, then 10 A relay, then speed trim moduleRelay module 1, points 1 to 6
Fill solenoidFVFuse, then 10 A relayRelay module 2, points 1 to 6
Drain valveDVDirect, 5 WRelay module 3, points 1 to 6
Low and high level switchLSL, LSHTwo wires eachInput module 1, points 1 to 12
Cassette seated switchZSTwo wiresInput module 2, points 1 to 6
Pull buttonOne per cassette, on the stripInput module 2, points 7 to 12
Flow sensorFTThree wires: 24 V, 0 V, pulseOption module inputs X1 to X6
Leak sensor; on-battery signalOption module inputs X7, X8
Light relay boxLT24 V signal, one per pairOption module outputs Y1 to Y3
Light dimmingLT0 to 10 V, one per pairAnalogue module, 1 to 3
pH and EC circuitsPH, ECProbe lead to its circuit in the panelBay computer bus, addresses 11 to 16 and 21 to 26
Dosing pumpsDA, DB, DD, DUPower through the dose-permit relayBay computer bus, addresses 31 to 84
Temperature probeTTThree wiresBay computer, one-wire pin
Air sensors, light sensor, fan controller, CO₂Through the multiplexerMultiplexer channels 0 to 6

Done when: Every row of the table is wired, labelled and checked with the meter.

8.3 Mount at the bay, with the dosing box, switches and jugs

Builder
lift aislemiddle aislebay paneldosing boxpump switchesstock jugs
A control enclosure on a rack post with rows of small coloured dosing pumps under it and a strip of round switches below
Panel, dosing pumps and the switch strip, from the model.

Parts

  • C14 Dosing box · 1
  • A18 Dosing pump · 24 per bay, 8 for the first pair
  • A19 Dosing tube and fittings · 6, 2 for the first pair
  • C19 Hand-off-auto switch, one per pump · 6, 2 for the first pair
  • C15 Bay stock jugs and tray · 1
  • C18 CO2 sensor · 1

Done when: Each pump runs from its switch in Hand with the controller off. Each dosing pump gives the same weight three times.

8.4 Programs

Whoever writes the software
Agent, dashboards, scriptsread data; change setpoints inside limitsLab computer (edge PC), server cabinetall logic, database, one API, alarmsAPI onlyPoE network switchBay A1 panelPLCinputs, outputs, watchdogBay computerpasses probes and dosingpumps, fill, drainlevel, leak, seatedlight dim, frame, blindspH, EC, temperature24 dosing pumpsair T, RH, CO2, light, fansNo rules here except the watchdog.Lost heartbeat: valves shut, pumps run.Bay A2 ... B2 panelPLCinputs, outputs, watchdogBay computerpasses probes and dosingpumps, fill, drainlevel, leak, seatedlight dim, frame, blindspH, EC, temperature24 dosing pumpsair T, RH, CO2, light, fansNo rules here except the watchdog.Lost heartbeat: valves shut, pumps run.Water zone panelPLCdemand pump, master valves, RO, totestote low level x3, header pressurerack fill meters x2, leak sensoremergency stop statusAny leak input closes both master valvesand stops the demand pump.
Safety rules live in each bay's controller. An agent reaches the hardware only through the edge PC.

None of this software exists yet. See Open gaps.

Done when: Each rule in sections 7 and 9, and the watchdog, has been triggered on purpose and seen to work.


Phase 9. Calibrate and test the first pair week 5

9.1 Power and battery

Builder, checked by the electrician
A steel cabinet on short legs at the end of a rack, under a power supply panel
Battery cabinet under the supply panel at the east end of the rack.

Parts

  • D01 24 V supply with battery backup, 20 A · 1 now, 3 in all
  • D02 Backup battery, 24 V 100 Ah · 3, later
  • D03 Battery cabinet · 2, later
  • D03b Battery disconnect and fuse · 3, later

Done when: 24 V at the bay panel with the supply on. With a battery fitted, 24 V stays when the supply is unplugged.

9.2 Fill, set the flow, calibrate

Builder

Parts

  • F09 Calibration solutions, storage solution, spare probes · 1 set

Tools Bucket, kitchen scale, timer, handheld pH and EC meter, calibration solutions, wash bottle.

Done when: Flow reads 4 L/min, probes agree with the handheld meter, and each dosing pump repeats within 3 percent.

9.3 Run every test

Builder
TestPass when
Run 24 hours on waterNo drips anywhere. Drip tray dry.
Flow to each cassette4 L/min with the pump at or below 22 V
Flow from each of the 8 channels, cup and timerEach within 15 percent of the mean
Film in the channelWet across the floor, no dry strip, no pooling
Tank temperature after 24 hours, lights onNo more than 3 °C above room
Pull and reseat each cassette 20 timesPump stops first; drips land in the catch, none on the tier below
Dye in one loop for a weekNone in the partner cassette's tank or on the tier below
Pour 1 L into each drip panAll of it reaches that cassette's own tank
Turn the controller off, pump switch to HandPump runs; alarm sent when the controller returns
Fill: hold the solenoid open by handFloat valve stops the water below the high switch
Fill: unplug the low switchPump stops within 2 seconds
DrainTank at low level in under 10 minutes
Each dosing pump, 30 seconds into a cup, 3 timesWithin 3 percent of each other
Hold pH 5.8 and EC 1.5 for 48 hourspH within 0.15, EC within 0.1 mS/cm
Light map, 9 points per cassetteMean 200 µmol/m²/s or more; dimmest 70 percent of brightest
AirUnder 2 °C rise; 0.3 m/s at mid-canopy
Pull the plug on the 24 V supply for 4 hoursPumps run 1 minute in 5; alarm sent; battery use projects to 24 hours or more
Unplug the bay network cable for an hourSafe state within 10 seconds; pumps keep running; normal control returns with the cable
Pull a full cassette from tier 3 with the liftOne person, no spill, rack does not move
Push in and pull out each cassette 50 timesLatches by itself every time; one pull on the grip bar releases it
Pull on the frame with 50 lb, grip bar untouchedThe cassette does not move

Done when: Every row has a result, a date and initials.


Phase 10. First crop weeks 6 to 7

10.1 Mix stock and plant

Builder, with the plant science leads
Rack header3/4 in, 20 psiMaster valveone per rackFill meterone per rackFill valve FV24 V, closed at restFloat valvesecond shut-offfalls through an air gapTank, 15 gal. Works at 10 in depth, about 12.5 galpHECTLSHLSLprobes and level switches at the aisle end of the tankABpH-pH+4 dosing pumpsin the bay dosing boxbay jugs in a spill tray, under 3 ft from the pumpsValveand strainerP24 V pumpDrain valve DVclosed at restDrain line1/2 in under rampFloor drainriser, 1/2 in PVClift 1.6, 4.1 or 6.6 ftCassette4 channels, 1 L/min eachFlow FTthen fixed nozzlesDrip pantiers 2 and 3, drains to the returnsensor portgravity return: own trough, 1-1/2 in downpipe, mesh sock
One loop. Clean water in at the top, the pump and cassette at the right, dosing at the bottom left.

Where seedlings come from is not planned yet. See Open gaps.

Done when: Two cassettes of plants have grown for two weeks with pH within 0.15 and EC within 0.1 of target.


Phase 11. The other bays about one bay a week

11.1 Stage 2: finish bay A1

Builder

Done when: Six cassettes have grown a crop in bay A1, and the change list is written.

11.2 Stage 3: bays A2, A3, A4, B1, B2

Builder

Parts

  • D01 24 V supply with battery backup, 20 A · 3 in all
  • D02 Backup battery, 24 V 100 Ah · 3
  • D03 Battery cabinet · 2
  • D12 Drain line and aisle cover · 2
  • D13 Drain tube and fittings · 1 lot

Done when: Thirty-six cassettes run and the room stays inside its limits.

11.3 Drain line and ramps

Builder
Inside the rack: green return pipes into the tanks and pale blue fill pipes
Inside the rack. Green returns, pale blue fill lines.

Done when: Each tank pumps out to the drain in under 10 minutes.


Phase 12. The other zones any time

12.1 Lift, stairs and winch

Builder, after a quote
1Raise and roll inRaise the deck 1 in above the tier.Roll in until the hooks are over the dock bar.2Lower on to the barLower 1 in. Both hooks sit on the bar.The deck cannot move away from the rack.3Cassette on the deckThe cassette crosses on to the deck.The deck catch springs up behind it.To undock: raise 1 in, roll back.dock bar on the racklift deck with hookdeck catchcassette
Docking the lift deck to the rack.

Parts

  • F01 Mast lift · 1
  • F02 Pull winch · 1
  • F02b Deck docking kit · 1
  • F03 Rolling stairs, 4 step · 1

How a cassette is pushed back in at tier 3 is still open. Do not use the stairs to carry a full cassette.

Done when: One person pulls a full cassette from tier 3 with no spill and the rack does not move.

12.2 Robot floor pots and vine bay

Builder and a fabricator

Parts

  • G05 Pots on the robot floor · 1 lot
  • H01 Strut channel, 1-5/8 in, 10 ft · 26
  • H02 Strut fittings · 1 lot
  • H03 High-wire hooks with twine · 1
  • H04 Drip stakes, 2 L/h · 1
  • H05 Vine irrigation set · 1
  • H06 Top light for vines · 2
  • H07 Side bar hangers and cords · 1 lot

Done when: Pots and vines are watered with no run-off on the robot lanes.

12.3 Network, cameras and server cabinet

Builder, with IT

Parts

  • D18 PoE+ network switch, 24 port · 1
  • D19 Network cable and outdoor-rated patch leads · 1 lot
  • G08 Lab camera screen and three cameras · 1 lot
  • G13 Server cabinet · 1

Done when: Every bay panel and camera answers on the network.

12.4 Entry room, benches and signs

Builder

Parts

  • G01 Robot lockers · 2
  • G02 Roll-in cage · 1
  • G03 TV and wall mount · 1
  • G04 Desks and benches · 1 lot
  • G10 Floor tape and signs · 1 lot
  • G11 Healing bench · 1
  • G12 Charging and docking bays · 1 lot

Done when: The floor markings match the plan.


Phase 13. Routine once it runs

WhenDo
Every dayRead the alarms. Walk both aisles: look for a dry channel, a drip, a dark light bar, a stopped fan. Check the tote level.
Every weekCheck each tank's pH and EC against the handheld meter. Recalibrate a probe that differs by 0.2 pH. Top up the bay jugs. Empty the mesh socks.
Every monthRefill the stock drums. Wet each leak sensor to test it. Press each ground-fault test button. Pull the 24 V plug for ten minutes to test the battery.
Every crop changePull the cassette. Pump out the tank, rinse, pump out again, wet-vacuum the last inch. Scrub channels at the sink. Clean the conductivity probe. Lift each level float by hand.
Every yearReplace pH probes that no longer calibrate. Their life is about 2.5 years. Re-do the rack pull test.

Open gaps what this plan cannot yet tell you

GapWhat is missingWhat to do
Cassette drawing, five items to confirmThe shop drawing in phase 6 is drawn from the model. Channel size, the clear gap at each slot, slide strip spacing, which end is high, and the plant hole size are not measured.Confirm all five in task 0.2 before cutting. Build two cassettes before the other 34.
Latch partA small rotary latch is chosen from a search result. Its lever style, release force and fit are not checked.Buy two in wave 1. Run the latch tests in task 6.2 before buying 34 more.
Controller and computer softwareThe rules are written in the build spec, section 9. All logic now runs on one lab computer. That program, the plain input and output program in each controller and the bay computer relay program do not exist yet.Blocks phase 9. The first pair can run on a simple timer program for the water tests.
Bay panel sizeThe 16 × 14 in enclosure was chosen for three loops. Six loops add relays, probe circuits and speed modules.Lay the parts out on paper at full size before ordering C11. A larger enclosure may be needed.
Pump price and US sellerThe pump curve is verified. The price and the seller are not.Get a quote in wave 1.
Light bar price108 bars, priced by guess.Get a distributor quote in wave 1.
Battery supplyIt is not confirmed that the chosen supply charges a lithium iron phosphate battery.Check the data sheet before ordering D01 and D02.
Pump gap and jug stripSix pumps share a 10 in gap, and the jugs a 10 in strip.Cardboard mock-up in phase 5.
Probe lead lengthLeads are 1 m. The south tanks are farther from the panel.Order longer leads for three tanks per bay, or fit a small box on the south face.
SeedlingsThe layout has no nursery.Needed before phase 10. Ask the plant science leads.
Stock strength and targetsStrength of stock A and B, and target EC and pH per crop, are not set.Needed before phase 10.
Lift in the middle aisleThe lift is drawn only in the south aisle. Two thirds of the cassettes face the other aisles.Needed before the bays beyond A1 are loaded.
Facilities answersWater, drain, power and room air.Blocks phases 3 and 4.