Work with usFifteen steps take a bare rack bay to six running cassettes. Every picture is the same cut through the bay, looking along the rack. Parts you fit in a step are amber. Parts already fitted are grey.
| Kept | Where it goes | Used in |
|---|---|---|
| Two aluminium racks, 18 ft 8 in × 5 ft 8 in × 9 ft | Kept as racks A and B at the positions on the plan. Check where they stand now; a rack may have to move. Casters come off; levelling feet go on. Six layers become three tiers. | Step 1 |
| NFT channels and lids | Cut into 32 in pieces, four to a cassette. 144 pieces needed. | Step 15 |
| Long LED bars, over 7 ft | Too long for a bay. They move to the pot rows, the vine bay and the mung and saffron racks. | Not in this guide |
| Three 275 gal totes | Clean-water store in the water zone at the west wall. | Water zone |
| Filter housings | Ahead of the reverse osmosis unit. | Water zone |
| Transfer pump | Tote-to-tote moves only. A new demand pump feeds the header. | Water zone |
| Sink, taps, floor drains, lined trough | Unchanged. The drain line in step 10 ends at the middle-aisle floor drain. | Step 10 |
| Wall disconnect and ceiling power drops | Main switch and feeds for the rack outlet strips, if Facilities agrees. | Electrician |
| Two pallet racks with flood trays | Mung and saffron racks, kept where they are. | Not in this guide |
| Buckets and the bucket frame | Pots on the robot floor and the ten vines. | Not in this guide |
| Steel tables and wire shelving | Planting table, two harvest tables, storage runs. | Not in this guide |
| Handheld pH and EC meter | Reference for every tank probe. | Step 11 and weekly |
| Two-part fertiliser and pH down | Stock A and B and the acid jug. | Step 12 |
| Small computers and probe circuits on the pending list | Check them against the order list before buying more. | Step 12 |
Leaving the rack area: the third rack, the grow tents, the casters, the shared feed manifolds, and the old pumps and reservoirs. Count the old pumps and reservoirs before discarding them. They may serve the vine bay.
PVC cutter, primer and cement. Step drill and hole saws for the covers. 4 ft level. Luggage scale. Crimp tool and ferrules. Multimeter. Label printer. Kitchen scale and a cup. Bucket and timer. Light meter. Cardboard and a knife for mock-ups.
Check: Pull 50 lb sideways at 7 ft with a luggage scale. No foot moves.
Check: Pour 1 L on the deck. It stays inside the lip and the sensor trips.
Check: Six tanks fit between the posts with the covers on. A 10 in gap runs between the two rows.
Check: Fill the tank to 4 in. No drip at the bulkhead or the unions with the ball valve open.
Check: Six risers per bay, each traced by hand from one pump to one cassette.
Check: Run the pump. Catch each nozzle in a cup for 30 seconds. The four agree within 15 percent.
Check: Pour 2 L into each trough. All of it reaches the right tank.
Check: Pour 1 L into each pan. All of it reaches that cassette's tank.
Check: Hold a solenoid open by hand. The float valve stops the water below the high switch.
Check: Open one drain valve with the pump on. Water reaches the floor drain and nowhere else.
Check: Lift each float by hand. The right input changes on the controller.
Check: Each pump runs from its switch in Hand with the controller off. Each dosing pump gives the same weight three times.
Check: Nine light readings per cassette. The mean is 200 µmol/m²/s or more.
Check: Under 2 °C rise from intake to exhaust with the lights at full.
Check: Pull and reseat each cassette 20 times. The pump stops first each time. No drip reaches the tier below.
Check: pull the supply's plug for 4 hours. Pumps run 1 minute in 5 and an alarm is sent.
Add tiers 1 and 2 of bay A1 to the same panel. Then build A2, A3, A4, B1 and B2 the same way. Log room temperature and humidity as each bay starts. Stop adding bays if the room passes 26 °C or 75 percent humidity.
The full test list and pass values are in section 11 of the build spec and on the Test log sheet of the order list.
| Device | Tag | On the way | Lands on |
|---|---|---|---|
| Pump | P | Fuse, then hand-off-auto switch, then 10 A relay, then speed trim module | Relay module 1, points 1 to 6 |
| Fill solenoid | FV | Fuse, then 10 A relay | Relay module 2, points 1 to 6 |
| Drain valve | DV | Direct, 5 W | Relay module 3, points 1 to 6 |
| Low and high level switch | LSL, LSH | Two wires each | Input module 1, points 1 to 12 |
| Cassette seated switch | ZS | Two wires | Input module 2, points 1 to 6 |
| Pull button | One per cassette, on the strip | Input module 2, points 7 to 12 | |
| Flow sensor | FT | Three wires: 24 V, 0 V, pulse | Option module inputs X1 to X6 |
| Leak sensor; on-battery signal | Option module inputs X7, X8 | ||
| Light relay box | LT | 24 V signal, one per pair | Option module outputs Y1 to Y3 |
| Light dimming | LT | 0 to 10 V, one per pair | Analogue module, 1 to 3 |
| pH and EC circuits | PH, EC | Probe lead to its circuit in the panel | Bay computer bus, addresses 11 to 16 and 21 to 26 |
| Dosing pumps | DA, DB, DD, DU | Power through the dose-permit relay | Bay computer bus, addresses 31 to 84 |
| Temperature probe | TT | Three wires | Bay computer, one-wire pin |
| Air sensors, light sensor, fan controller, CO₂ | Through the multiplexer | Multiplexer channels 0 to 6 |
Six of each device per bay, in the order T1-S, T1-N, T2-S, T2-N, T3-S, T3-N. Use an M12 connector at each field device so it swaps without rewiring. Set each bus address on the bench and write it on the part.